Structural |
|
Facade
|
RCC Framed Shutters with Raft Foundations
and Flat Slabs |
Green Building compliant Continuous double glazed ribbon window facade, and Aluminum cladding is provided. The Sixth and seventh floor balconies as a relief adds to the aesthetic appeal. |
 |
 |
 |
Finishes
|
|
Flooring
|
External Walls finished with Texture Pain |
The floors within the tenants area is finished as cast and Granite &vitrified tiles are provided in the lobbies and main stairs, Kota stone provided in the emergency stairs
|
 |
 |
 |
Lifts
|
|
Garage / Car Parks |
Five State of the art 20 passenger *MITSUBISHI Passenger elevators with a speed of 1.75/m/sec are provided per Block and Mitsubishi Service Freight One Ton elevators are provided per Block
|
Car Parks are about 765 in the basements and at the surface level. Allocation will be proportional to the space taken up by each tenant, which would translate to about One Free car park for every 775 sq.ft leased.
|
| |
|
| |
|
|
 |
 |
Electric |
Power supply |
Electric supply is provided from the TNEB Grid Sholinganalur 400/230 kV S/S, 2x315 MVA and also 200 MVA 400/110kV GExternal 3,000KVA per block,and routed through two Transformer 1,600 KVA X 2 per block to cater 300-350KVA per Floor
|
1.10KVA of Power connection is provided per 100 sft. of carpet area. Any additional power, if required, would be provided, if technically possible, at additional cost. |
|
|
Generators |
|
100% Back up |
Three Backup generators of 1250 KVA are provided for each block on the stilts with fuel tank for 8 hours of and an additional underground sump to store about 25,000 liters of fuel.
|
|
100%Power back can be provided from the generators with a floor distribution of about 300-350 KVA power supply (approximately) per floor. The charges will be based on the costs then prevailing for fuel and taxes if any. |
|
|
|
Air condition |
Connectivity |
Three + one spare Carrier Kruger 330TR Air Cooled chillers are provided on the terrace of each block. The charges are for actual usage calculated by the BTU meters installed on either AHUs on all floors.
|
OMR being the preferred IT Corridor all the major Bandwidth operators have a presence here. Exclusive space is to be provided for Bandwidth Operators, and Wi-Fi towers on the terrace
|
|
|
|
|
|
|
 |
|
|
BMS
Building Management System Provided
|
 |
 |
Fire Safety
|
|
Water & Management
|
ring main Hydrants, alarms, smoke detectors sprinklers, and exits provided |
|
900,000 liters Storage sump and a OHT of 25,000 liters provided Water Treatment Plants and Sewage Treatment Plants are provided
|
|
|
|
|
|
Toilet |
|
Emergency
|
Male 8 EWCs & 6 Urinals on each floorFemale 10 EWCs on each floor Handicap Toilet 1 EWC on
each floor
|
Grundfos & Kirloskar pumps in basement
|